Recent Work



Cabell County Board of Education 

Project: Milton Elementary School – Site Package 

Engineer: McKinley Architecture and Engineering

Scope: Building demolition, clearing and grubbing, stripping over 15,000 cubic yards of topsoil, 70,000 cubic yards of excavation, building pad, retention pond with riser, 2,000 linear feet of HDPE storm sewer, 2,100 linear feet of sanitary sewer, sanitary pump station, 2,200 linear feet of water line, 3,300 linear feet of electrical conduit, 18 light pole foundations and 6,500 tons of base stone. 


West Virginia Division of Natural Resources

Project: Beech Fork State Park – Equalization Tank

Engineer/ Contact Information: Jason Dingess

Scope: Fabricate new 20,000 gallon equalization tank, 12” concrete foundation, 8” intake piping, 2” discharge system, 2” air system, FRP grating, new control panel, three 2” pumps, demolition of existing tank, and shutdown/ tie in less than three hours.


AB Contracting

Project: Valley Pointe

Engineer: The Thrasher Group

Scope: Clearing and grubbing of 6 acres, removal and reclaim of existing concrete pavement sections on site, erosion and sediment controls, excavation of 34,000 cubic yards of material, installation of 6,400 linear feet of HDPE storm sewer, 1,600 linear feet of sanitary sewer, 1,500 linear feet of water line, 10,000 linear feet of electrical conduits and site lighting, 4,000 linear of curb, 122,000 square feet of concrete stabilization, application of 6,000 tons of base aggregate.


WB Development

Project: Sugar Maple Phase II & III

Engineer: Cheat Road Engineering

Scope: Establishment of erosion and sediment controls for 40 acres of disturbance, combined excavation of over 90,000 cubic yards of material between both phases, installation of over 3,000 feet of HDPE storm sewer piping, 9,000 linear feet of conduits, 6,000 linear feet of concrete curbing, and cement stabilization of the road base before installing base aggregate.


AB Contracting

Project: Site development of the Bend at Meadow Valley
Engineer: The Thrasher Group

Scope: Clearing and grubbing, installation of erosion and sediment controls, excavation of approximately 23,000 cubic yards of material, installation of 4,000 linear feet of sanitary sewer pipe, 31 drop inlets, 1,600 linear feet of HDPE storm sewer pipe, installation of 3,660 linear feet of water line, 9,200 linear feet of electrical conduits, and 4,500 linear feet of concrete curb. 


City of Hurricane, WV

Project: Fire Station site work

Scope: Mass excavation for new fire station


Sugar maple Phase 3

When developers of Sugar Maple Ridge in Morgantown, WV discovered that Phase 3 of the development was short approximately 15,000 yards of dirt, they engaged Landcore for insight on potential redesign options. Landcore surveyed the site and found the necessary yardage. In addition to finding the required material, team members were able to create seven more house seats to bring more value to the developer.

With the single-family homes being added to an existing design, additional grading was required to maintain existing utility constraints. Engineers finished the final design in early January, and with local utility companies already on site, the additional grade work needed to be completed without delay.

Developers again challenged Landcore to execute the required grading without causing delay to the local utility companies. How do you move roughly 7,000 yards of material with temperatures near zero degrees and still meet quality control requirements? You do not allow the dirt to freeze nor thaw. Landcore team members embraced the challenge and chose to move material 24 hours a day. Working with two shifts, team members were able to install the required toe-key drain and nearly 7,000 yards in just four days.

Choosing to work 24 hours a day proved to be the right decision. Members endured snow and temperatures well below freezing to complete the work, however, team members did not fail a single compaction test. When you have a team that shares a passion for construction, they encourage projects with challenges, and improvise to provide creative solutions that work.


IMG-1419.jpg

Putnam County Bank

In the summer of 2020, board members of Putnam County Bank chose Landcore to renovate and expand their Interstate branch located in Hurricane, WV. Landcore was fortunate to be involved early in the design phase and ultimately construct the project. Landcore’s scope of work entailed removal of several drive thru service counters to create a new green space and a new 5,000 square foot single story building addition. Designs also called for remodeling both floors of the existing branch to provide additional office space. In all, the newly renovated branch will include roughly 10,000 square feet of office space for the banks expanding loan department.


Greene County Transfer Station

After deciding to expand their operations in Mt. Morris, PA, Mountain State Waste (MSW) turned to Landcore to assist them through all phases of the project. Mountain State Waste chose Landcore based on the relationship formed from prior projects.

The goal of the project was to convert an existing warehouse facility into a combination facility that would house MSW’s Mt. Morris operation including administrative offices, maintenance shop, and the Greene County Transfer Station. Mountain State Waste relied on Landcore engineers to work with various design firms, local permitting offices to design and build the project. Once permits were in hand, the clock began. Landcore crews were able to have the $1.7 million dollar facility operational in just over 90 days. The entire project was constructed while the facility served as a hub for MSW’s northern operations. The project management team comprised of team members from MSW and Landcore elected to have an onsite engineer from Landcore to facilitate changes in the design throughout the project duration. This allowed for in field design changes and ultimately accelerated the project schedule.

Landcore’s commitment to see a project through to completion, and the ability to self-perform many trades along with an internal steel fabrication team contributed to the success of this complicated and challenging project. 

dump.jpg

DJI_0230.JPG

Village of Sugar Maple Ridge Phase II

Landcore’s work on the Village of Sugar Maple Ridge involved erosion and sediment controls, storm water management, and earthwork for Phase II of the development. Excavation originally included 34,000 cubic yards of material, however, changes in design required Landcore crews to move approximately 45,000 cubic yards of material. Early in the project it was determined that Phase II would not balance. To acquire needed fill material, crews worked with developers to begin excavation of Phase III. This generated enough material to complete Phase II. Using GPS technology crews then provided as-built survey data of Phase III to engineers for future use in design of phase III.


Halstead Street Heavy Highway Construction

Landcore secured a contract to widen and reconstruct Halstead Street in April of 2020. Construction involved new storm water drainage improvements with the addition of a new MS4 retention pond. Over 1700 LF of storm piping was installed along the length of the project. The existing roadway was completely removed to subgrade and over 2,000 LF of the road was widened. Reconstruction included the placement of over 3,400 LF of combination curb and gutter with new asphalt pavement, guardrail and striping. Landcore team members worked with over 40 homeowners who lived along the road to successfully complete the project. Throughout the entire project, crews had to maintain daily access to the 40+ homes.

During reconstruction, crews experienced unsuitable soil conditions in numerous areas. Engineers with Landcore’s team worked with West Virginia Division of Highways personnel to develop solutions for overcoming the unstable soils while keeping the project on schedule and within budget.  

Street.jpg

Sludge1.jpg

Sludge Loadout Building

Late in 2019 Landcore’s team was able to secure a contract to build an addition for the City of Huntington’s Water Quality Board at their wastewater treatment facility. The scope of work included construction of a concrete masonry unit enclosure around an existing sludge loadout corkscrew conveyor system. Construction began in spring of 2020. The project management team experienced an increase in lead times due to COVID-19 delays, nevertheless, Landcore’s team worked with Water Quality Board personnel to have the facility operational while waiting for several components to arrive. Several design issues were discovered along the way, project managers and engineers with Landcore worked with the design firm, Potesta & Associates, Inc., to develop cost-effective solutions that allowed construction to continue unimpeded


West Virginia Army National Guard

When the West Virginia Army National Guard acquired the old Rite Aid warehouse in Poca, WV, they had no means to bring troop transports inside their secured facility. Working with ZMM Architects & Engineers, Landcore crews removed an existing truck ramp, canopy, and two garage doors to make room for new 20’ x 20’ access doors. The project schedule required team members to build a larger reinforced concrete ramp in January of 2020. Once the new ramp was installed, crews went to work enlarging the openings. Because the facility was secured, openings had to sealed up and reopened every workday to maintain a secured space. Crews self-performed all the demolition, concrete work, erection of structural steel, and masonry infills. Landcore also utilized the coating expertise of our sister company, Core Industrial Group, to coat various elements of the existing structure affected by the rework. Landcore was able to complete the work in 60 days with the assistance of valuable electrical and canopy trade partners.

poca.jpg

IMG_20190716_083648.jpg

AEP Central Machine Shop

In order to perform work for American Electric Power, companies must be a member of ISNetworld, and undergo rigorous audits and verifications of safety programs, insurance requirements, and maintain low experience modification ratings. In May of 2019, the AEP Central Machine contracted with Landcore Builders to renovate several of their offices, labs, and meeting rooms. Landcore team members worked on the project in phases to provide minimal disruptions to AEP personnel. In July of 2019, AEP representatives were pleased with the results of the first three phases and decided to award two additional phases to Landcore. In addition to the renovations, Landcore Builders has been awarded additional contracts to perform work associated with security upgrades as well as other various construction projects within the facility.


Mineral Wells Weigh Stations

Landcore Builders was selected by the West Virginia Division of Highways in March of 2019 for the construction of two new weigh stations along Interstate 77 in Mineral Wells, WV. In addition to building two new facilities, the project involved existing building demolition, a variety of concrete pavement repairs to include both partial and full depth pavement repairs, numerous utility and signage upgrades along the interstate, and the installation of new weigh bridges and measuring software at both locations.

Screen Shot 2019-07-11 at 2.18.36 PM.png

 
IMG_9000.jpeg

Harris Riverfront Park Skate Park

In March of 2019, Landcore Builders broke ground on Phase II of the Huntington skate park in Harris Riverfront Park. Early on crews realized that the planned elevations for the park would create multiple drainage issues for the existing skate park as well as the new phase. Landcore team members work with architects from Edward Tucker Architects to develop a new design that would eliminate the drainage issues while staying within the City’s budget. As the new design was being finalized, team members continued to work on various elements of the park, and were able to complete the entire project in five weeks.


Charleston Sanitary Board Building Addition

In February of 2019, Landcore Builders won a bid to construct an addition to an existing warehouse for the Charleston Sanitary Board. The addition involved the construction of a Parkline metal building and foundation design. In order to obtain addition space in a quick manner, Charleston Sanitary Board imposed a construction period of 90 days to manufacture and construct the building. Landcore representatives worked with Parkline to condense the lead times for the building, and were able to deliver the building to the Sanitary Board in 60 days.

IMG_3571.jpg

IMG_20190211_104555.jpg

Core Industrial Group

In March of 2018, construction began on the site development and building construction of 22,000 Sqft $3.2 million industrial facility for Core Industrial Group. Landcore Builders handled all of the design work and self-performed approximately 60% of the overall project. Site development included the construction of 1000 linear feet of roadway, utility installation, and construction of the building pad. In all, nearly 14,000 cubic yards of material was moved prior to beginning building construction. Several large-scale pieces of equipment within the facility required detailed concrete and steel work to accommodate the equipment. Construction of the facility was completed and turned over to the owner in seven months.


Big Sandy Superstore Arena

In November of 2018, Landcore crews began a beautification project around the Big Sandy Superstore Arena in Huntington, WV. The project involved removing and replacing existing sidewalks. In addition to new sidewalks, lighting improvements were made by adding additional street lights, and 14 new parking spaces were added to the facility with the creation of a new staff parking area. Crews worked around numerous events scheduled at the arena throughout construction including concerts that brought 8000-9000 people to the arena. During the events, all sidewalks, new and old, remained open to the public.

h town civic center.JPG

Core sidewalks.jpeg

Huntington ADA Ramps

In April of 2018 Landcore Builders was awarded the contract from the West Virginia Division of Highways to design and build ADA compliant curb ramps at 117 locations across Huntington, WV and Wayne, WV. Curb ramps were subjected to rigorous guidelines outlined by the United States Access Board Proposed Accessibility Guidelines for Pedestrian Facilities in the Public Right of Way (PROWAG). Construction began after the design phase in early July, and substantial completion was achieved in late September after final inspection with the WVDOH.


Huntington Physical Therapy

In the Spring of 2018, Landcore Builders began working with representatives from Huntington Physical Therapy on constructing a new location in Milton, WV. Landcore facilitated the design of the building as well as the overall site layout to meet the needs of the client. Several designs were created and value engineered prior to arriving at a design that met the client’s budget and needs. This new 4,500 sq. ft building will not only serve Huntington Physical Therapy, but will also have custom build outs for a national investment firm and a national insurance agency. Construction of this new building began in November and opened in early March.

IMG_3588.jpg

IMG-0145.JPG

Marco’s Pizza & Paradise Donuts

In 2017, Landcore Builders was contracted by R & J Development of Catlettsburg, KY for the construction of what would be the shell for a new Marco’s Pizza and Paradise Donuts. Before construction could begin, Landcore crews had to demo the existing carwash and relocate several utilities. While building the shell of the building, a relationship was formed with the Owner of Marco’s and Paradise franchise, and the decision was made to have Landcore complete the interior build out. In the end, Landcore met the compressed schedule for the entire project and come in under budget.


Cenergy

Cenergy LLC, a leader in natural gas metering and regulation stations, contracted Landcore Builders to design and construct a new office building in Milton. Landcore broke ground on the new 3000 sq. ft space in December of 2010. Despite winter weather conditions, crews were able to complete the building on time and under budget. Since completing the original office building, two more additions were made to meet Cenergy’s ever demanding growth bringing the total office space up to 5000 sq. ft. Over the years, Cenergy has entrusted Landcore Builders to complete several building renovations and maintenance projects throughout their four locations in Milton.

Cenergy.jpeg

milton+office.jpg

Unlimited PossAbilities 

In 2016, Landcore Builders began working with Unlimited PossAbillities, a repeat client, to design and build a new 10,000 sq. ft. office complex, with Unlimited being the anchor tenant.  The design called for the construction of two separate buildings, one for the main office and the other to serve as a primary activity building. The construction of the activity building required meeting numerous ADA guidelines due to the unique occupancy of the building. The main office building required custom build outs for additional office space that is home to a national legal firm as well as a national orthopedic firm.  Prior to construction of the new building, existing structures had to be removed from the site, and multiple utilities had to be relocated.  As stated above, Unlimited PossAbilites is a repeat client. Landcore built their original office building in 2011 and we were honored to be chosen to be part of their new adventure. 


Guyan River Public Library

In 2016, Landcore Builders, was contracted by the West Virginia Library Commission to construct a 2000 sq. ft library in Branchland, WV. During construction, Landcore team members worked with the local public service district and local landowners to relocate numerous underground utilities throughout the site. Construction of the new building was completed in under 100 days and ahead of schedule.

library.JPG

dr bowl.JPG

Bower/OBGYN Medical Office Building

In 2016, Landcore Builders constructed a 4000 sq. ft. medical office space for Dr. Brian Bower with Cabell Huntington Hospital Women’s Health Barboursville.  The two-story building was designed to mirror the Cabell Family Medical Center located within the same business park. Since the project was built on undeveloped land, it required working with local utility boards to orchestrate mainline extension agreements for multiple utilities.  The medical office housed a variety of rooms including exams rooms, laboratory space, and office space. 


Snap Fitness/Generations Physical Therapy

In 2014, Landcore Builders completed a total interior and exterior renovation of a 7500 sq ft space. The project involved fully renovating the interior space including the removal of interior walls as well as all of the mechanical components. Exterior improvements included the addition of storefront windows, new roof, and new façade.  Landcore team members were able to complete the project in 78 days, and worked with the owner to value engineer the project that resulted in significant cost savings for the owner. 

Sanp Fitness.JPG